Sober Home Presentation

Due to the opioid crisis and proliferation of treatment facilities and mainly sober homes in the south Florida community the Governor tasked our Palm Beach County State’s attorney to create a Sober Home Task Force, of which I am a member representing the Singer Island Community, under the guidance of the Singer Island Civic Association. We are the only community and Civic Association represented.

Park Avenue/Yacht Harbor Lift Station #10

March 20, 2017 Update

We wanted to inform you that Wharton-Smith, Inc. has been hired to take over the Rehabilitation and Replacement of Lift Station No. 10 Project that has been ongoing in your neighborhood.


Utility District Lift Station 10 & 50 Project Update
December 22, 2016

On October 25, 2016, the Utility District’s outside Attorney, Malcolm Cunningham (“Cunningham”), advised Close Construction, LLC (“Close”), that the Utility District Board voted to terminate Close for its persistent failure to perform the Work in accordance with the Contract Documents. Also on October 25, 2016, Cunningham advised Close’s surety, Hartford Fire Insurance Company (“Hartford”) of Close’s default, and of the Utility District’s termination of Close for default on October 24, 2016. Cunningham demanded that Hartford correct Close’s defaults and complete Close’s work and meet with the District on or before November 1, 2016, to discuss completion of the project. Cunningham told Hartford that time is of the essence as the wastewater collection system is in temporary bypass and therefore subject to sewage spills.

Hartford responded on October 28, 2016, that Close had vehemently denied that it is in default of its contractual obligations. Hartford stated it needed time before meeting with us to investigate Close’s claim, that it did not breach its contractual obligations and therefore whether the District was within its legal rights to terminate Close. In any event, Hartford advised that if it decided to complete Close’s scope of work, it would consider using Close to complete the Work. Hartford requested project documents to assist Hartford in its investigation which Cunningham forwarded to Hartford. Close also wrote to Cunningham to advise that it intended to stay involved in the completion of the contract.

Cunningham responded to Hartford and Close that Close would have no role in the completion of the Project based on its past failure to perform the Work per the contract and Close having lied about obtaining a permit from SFWMD to discharge ground water directly into Lake Worth Lagoon. Hartford and Close have seemingly acquiesced that Close will no longer be involved in the project. Not knowing how long Hartford would take before meeting with us, District staff contacted the second and third low bidders on the Project, Florida Design Contractors and Wharton Smith and requested that both review the Work at the Project and submit a bid to Hartford for completion of the Work to expedite completion of the Project. Both companies have inspected the existing Work on the Project and have reviewed critical documents which will facilitate their understanding of what is required to complete the Work.

On November 4, 2016, Hartford notified us through its newly retained attorney, Bruce King that Hartford hired an engineer, Don Eckler of Coral Springs to assist it with its investigation of the Project and that Hartford met with District staff on November 15, 2016, to “discuss various options regarding the completion of the project….” Our project engineer is accompanied Mr. Eckler on a tour of the project on Monday, November 14, 2016, in advance of the meeting. We will update you after the meeting concerning how we propose to complete the project.

On November 15, 2016, the Riviera Beach Utility District staff along with our project engineers and our attorney, met with representatives of Hartford Fire Insurance Company (“Hartford”), the surety company for Close Construction LLC (“Close”), along with Hartford’s lawyer and its engineer. We discussed the facts leading to Close’s termination, the status of the Project site and the completion of the Project. Hartford expressed its interest in completing the Work. Recognizing that time is of the essence, Hartford agreed to provide a timetable for contracting with a completion contractor and restarting the work. The District staff agreed to furnish Hartford with certain critical documents. We expect to provide a further update after we
receive Hartford’s timetable and indication as to which contractor will serve as its completion contractor. On Tuesday, November 22, 2016, an engineering firm hired by Hartford will begin meeting with Florida Design Contractors and Wharton Smith to further evaluate both lift station sites.

Recently, Hartford Fire Insurance Company (“Hartford”), notified the Riviera Beach Utility Special District (“District”), that it has no obligation under the bond to takeover and complete the Work–only the payment of $3,799,022, the penal sum of the bond in the event of Close’s default under the bond. Yet Hartford has expressed “it would appear mutually beneficial for Hartford and Riviera to reach an agreement as to the completion of Close’s Work.” The negotiations have taken the form of Hartford seeking waivers of certain provisions of the contract documents that reduce the time and cost of Hartford’s completion of the contract.
The Utility District has steadfastly maintained that Hartford is bound unto the District for the payment of the bond amount for performance of the contract “at the times and in the manner prescribed in the contract” and that the District would insist upon compliance with the contract documents. Notwithstanding the activities described above, Hartford has yet to commit to takeover and complete the Work. By letter dated December 9, 2016, the District imposed a deadline of December 15, 2016, for Hartford to advise the District of its intention regarding taking over and completing the Work. Hartford indicated that it has solicited bids from several companies and expects a response from those companies soon. On December 21, 2016, Attorney Cunningham requested a commitment from Hartford to take over the project by January 2, 2017, or the District will move forward with completing the project by whatever mean available.

In the interim, the Utility District took steps to install new bypass pumping equipment at lift station 10 on Singer Island to help reduce the noise caused by the current equipment and increase efficiency of the temporary operation and going to try using misting machines to help address the complaint of an odor coming from the lift station.

The Utility District is working diligently to complete this project and we truly apologize for any inconvenience to the residents.

The City apologizes for this inconvenience, and let me assure you staff is working constantly to remedy that situation and bring the project to completion. If you notice, the City makes every effort to monitor the lift station daily to ensure no additional issues arise, and address the resident’s concerns.


JANUARY 11, 2017 … MESSAGE FROM COUNCILWOMAN, DAWN PARDO:
On December 22, 2016, the City placed an update on the activities related to the project on the City’s website. Since the City terminated the agreement with the original contractor on October 25, 2016, the City has been working with the Surety Company to select a new contractor to complete the project. The Surety company solicited bids in early November 2016 and received responses from two companies in late December 2016. We anticipate bringing an agreement to the City Council around January 25, 2017, to recommend a selection of a new contractor to complete the project. Based on my discussions with staff, the new contractor anticipates completing the project in approximately 180 days. Again we apologize for the delay but let me assure you the City is work diligently to complete this project so we can return that area to normalcy for our residents and improve the conditions at that lift station.

Should you have any questions or if I can be of further assistance please don’t hesitate to contact me, Troy Perry or Danny Jones.


JANUARY 16, 2017 UPDATE:
The City must follow the State mandated procurement procedure. The item will go to council next week for approval and then the new contractor will be able to complete the project. He will be on a tight schedule. We all want this project completed immediately. Thanks again for your patience.

Dawn Pardo
Councilwoman, District 4
dpardo@rivierabch.com

Singer Island Proposed Development

The developer will be going before the Riviera Beach CRA Commission on February 22, 2017 with the proposed land use, zoning changes, special exception and plat application.

2017 SICA Communications will be Electronic

Watch your inbox for the SICA 2017 Members’ Meeting e-Notices.

Frankel Announces Breakthrough on Group Homes in Neighborhoods

Congresswoman Lois Frankel (FL-22) is pleased to announce that today’s Joint Statement from the Department of Housing and Urban Development (HUD) and the Department of Justice (DOJ) will provide cities with the legal clarity they need to maintain the safety and character of their communities while protecting the rights and needs of people with disabilities, including those recovering from drug addiction.

Five Days for a Fane Lozman Street Address

A judge Monday gave Riviera Beach five days to assign activist Fane Lozman street addresses for the five Singer Island lots of what the activist calls his “Renegade” complex.

Mingle and Jingle December 1

In lieu of a December SICA meeting, SICA asks that you join us in helping Council-woman, Dawn Pardo, once again, provide thousands of toys to the city’s most needy children. It is Councilwoman Pardo’s wish that “Every Child Should Smile on Christ-mas Morning” in Riviera Beach.

Special Meeting – Park Avenue Lift Station

Dear Singer Island Residents,
A year ago, the City of Riviera Beach Utility Special District hired a contractor to retrofit the lift station on Park Avenue. Since then, we have experienced delays and other issues with the contractor. Last Monday, I made a motion to terminate the contract and hire a new contractor to complete the project.

Operation Hilton Helps Haiti

Join us as we collect dry goods, canned goods, clothing, linens and shoes to ship to Haiti after the devastation of Hurricane Matthew.

Meet and Greet the Candidates

Singer Island Residents – Be our guest for a candidate meet & greet for those on the November ballot. Palm Beach Shores Community Center on Monday, October 10th.

Next Page »